Pakistan's Bottom-Up Solar Revolution and What It Means for the Global South

Over the past four years, Pakistan has undergone one of the fastest consumer-driven energy transformations ever recorded. Without government subsidies, and often in the face of regulatory barriers, millions of households and businesses installed rooftop solar, importing nearly 46 GW of panels from China, almost equalling the country’s entire official generation fleet. The result is a system under profound stress: unaffordable grid electricity, stranded fossil fuel contracts, and a planning apparatus that could not see the revolution it was living through.

This report draws five lessons from Pakistan’s experience that are directly relevant for energy policymakers across the Global South — where the same forces of cheap solar, unreliable grids, and lock-in contracts are converging.

Five lessons from Pakistan

FACT FROM PAKISTAN
Grid electricity price increase since 2021, bills now exceed household rent in major cities
+ 0 %
FACT FROM PAKISTAN
Circular debt in FY2024, driven by legacy capacity payments and under-recoveries passed on to consumers
PKR 0 tn

1. Electricity price levels and rate design

Unaffordable grid electricity is the single biggest driver pushing Pakistani consumers toward solar self-generation. Flat, time-invariant tariffs make the grid uncompetitive even when generation costs fall, and legacy costs embedded in bills distort price signals for everyone.

FACT FROM PAKISTAN
Share of the electricity tariff going to capacity payments by FY2023–24, up from 41% just two years earlier
0 %
FACT FROM PAKISTAN
Estimated annual losses from stranded LNG contracts — Pakistan is cancelling ~45 of 120 contracted cargoes per year
$ 0 M

2. Capacity payments and take-or-pay contracts

Pakistan’s 1994 capacity payment regime was designed to attract private investment. By the 2020s it had become the primary driver of unaffordable tariffs , and the solar revolution it triggered is now leaving those same power plants idle. Take-or-pay LNG contracts signed before demand collapsed are adding hundreds of millions in annual losses.

FACT FROM PAKISTAN
Estimated unregistered behind-the-meter solar capacity, against just 6 GW of registered net-metered installations
~ 0 GW
FACT FROM PAKISTAN
Solar modules imported from China in four years, nearly equal to Pakistan's entire official installed generation capacity
0 GW

3. Electricity system planning and tracking distributed solar

Pakistan’s planning system was built to track large grid-tied plants, not millions of behind-the-meter systems. The result: national demand forecasts and investment plans were working with data that missed the most consequential shift in the energy system. Planning in the dark creates costly overinvestment in generation that is never needed.

FACT FROM PAKISTAN
Year-on-year fall in commercial sector grid electricity consumption in 2025 as businesses shift to self-generation
~ 0 GW
FACT FROM PAKISTAN
Battery energy storage imported in 2024 , projected to reach 8.75 GWh by 2030, or 26% of projected peak demand
0 GWh

4. Self-consumption and prosumer policies

Pakistan’s net metering policy, introduced in 2015, has been progressively tightened as solar scaled beyond what the policy was designed to manage. Flat-rate compensation for surplus electricity is becoming economically irrational as solar oversupply grows at midday. The next wave,  battery storage,  is already arriving and will deepen the shift.

FACT FROM PAKISTAN
Critical sections of Pakistan's 500 kV and 220 kV network are operating at or above capacity, severe overloading documented by NEPRA
0 kV
FACT FROM PAKISTAN
Industrial sector grid electricity consumption in 2025, deepening the revenue shortfall and making tariff-only financing unviable
- 0 %

5. Grid expansion planning and financing

As generation costs fall, grid investment needs are rising, but consumer tariffs, already stretched to breaking point, cannot finance the required upgrades. Pakistan already relies on its Federal Public Sector Development Programme to co-finance major transmission projects. The grid-as-public-infrastructure model is the only viable path forward.

Learn more in our paper

The full paper develops these five lessons in detail, drawing on the most recent data on Pakistan’s electricity sector and situating the country’s experience within the wider energy transition unfolding across the Global South. It is intended as a practical reference for legislators, regulators, and energy ministry officials shaping rate design, capacity contracts, and grid planning in the years ahead.

Related Activities

The Global Renewables Congress is made possible through the generous financial support of the Deutsche Bundesstiftung Umwelt (DBU — German Federal Environmental Foundation) and the Climate Emergency Collaboration Group (CECG).